Rag intrepid reporter Geoff Page checked out what was going on at the foot of Narragansett.
The Rag was prompted by a reader who requested we investigate the scene, and “request immediate clarification regarding the apparent staging and anticipated installation of fencing at the western terminus of Narragansett Avenue in Ocean Beach, near the coastal open space and shoreline access points adjacent to the pier area.”
Instead of a written report, Geoff offered these photos. (See above)

The vice-chair of the OB Planning Board offered these points in a recent comment to an article about the “bloated bureaucracy” and unfinished projects in the City of San Diego:
Narragansett Avenue Access Stair Repair
CIP B18026
Preliminary Engineering Start: Q4 2017
Design End: Q2 2025
Construction Start: Q1 2026
Total Project Cost: $2.21M
Construction Contract Value: $598.31K
$1.6M in design fees to do repairs to an existing stair?
City of SD is like an out of network ER when it comes to our tax dollars.