State commission approves Sunrise Powerlink project – opponents set to appeal

by on December 19, 2008 · 0 comments

in Economy, Energy, Environment, Organizing, San Diego

December 18, 2008

— The California Public Utilities Commission on Thursday cleared the way for construction of the Sunrise Powerlink, a contentious transmission line that promises to bring more reliable and renewable power from the Imperial Valley to San Diego. The 4-1 vote allows San Diego Gas & Electric Co. to move forward with the 123-mile, $1.9 billion power-line project, which could deliver enough electricity to serve 650,000 households.

“It’s something we really feel is in the best interest of our customers and in the best interest of the state in furthering a policy on renewables,” SDG&E President Debra Reed said. “Our plans are to move forward with construction of the line as soon as we possibly can.”

That may be awhile. Power line opponent Michael Shames, executive director of San Diego’s Utility Consumers’ Action Network, said a legal challenge is being prepared. “We expected this decision from Day One, and we’ll appeal,’ he said. “They ignored the facts on cost and reliability issues.”

Meanwhile, the full effect on ratepayers has not been determined. Reed said the transmission line will have a net benefit to the utility’s 1.4 million customers by providing more reliability and flexibility once the on-switch is thrown in 2012.

Customers may have to advance some of the construction costs, but will see a bigger return over time in energy savings, she said. “It will have a net positive benefit to customers financially,” Reed predicted. According to estimates by SDG&E and the commission, the line will save ratepayers $100 million to $200 million annually. Opponents, including Shames, dismissed those figures as exaggerated.

The decision was a significant win for San Diego Mayor Jerry Sanders, the region’s business leaders and Imperial Valley planners who see their desert as the renewable energy hub for California.

Gov. Arnold Schwarzenegger, who had lobbied for the project, issued a statement saying Sunrise “plays a critical role in California’s efforts to achieve energy independence – it will deliver clean, renewable energy and open the door for additional green investments in the Imperial Valley at a time when our economy could use the help.”

At the same time, it was a disappointment to for many environmentalists, who worry about the effects of 150-foot-tall towers on unspoiled deserts and mountains. “Corporate profit won out today,” said the Sierra Club’s Micah Mitrosky.

Nevertheless, environmentalists took solace in the fact that they blocked SDG&E from running the transmission line through Anza-Borrego Desert State Park, as originally proposed. The route approved Thursday runs along Interstate 8, skirting edges of the Cleveland National Forest.

Residents of that area said they were disappointed by the decision.  “It’s just destroying what we have back here,” said Bev Esry, chairwoman of the Campo-Lake Morena planning group. “I think it’s a horrendous decision.”

County supervisor Dianne Jacob, who represents East County, called the Sunrise Powerlink “a $2 billion travesty.” “This line is not needed,” she said. “There are better alternatives.”

The battle over the transmission line has been drawn out over three years, generating numerous marathon public hearings by the PUC and 11,000 pages of environmental studies. By the time the commission met Thursday, there was little doubt SDG&E would secure permission. Left undecided was just how tough an approach the commission would take toward requiring renewables. In the end, SDG&E won out when the majority voted for a plan advanced by Commission President Michael Peevey that was absent absolute regulations mandating the types of power that could be carried over the line.

The vote overruled attempts by Commissioner Dian Grueneich to draft tighter restrictions requiring proof from SDG&E that the line would be used for renewable energy.

SDG&E had said it would commit voluntarily to renewables from various sources, including the budding thermal, wind and solar industries in the Imperial Valley. The utility is facing a state mandate to generate 20 percent of its power from renewable sources by 2010, but currently has not yet surpassed 7 percent.“It does not impose any enforcement obligations,” Grueneich said of Peevey’s proposed decision.

Reed bristled at suggestions that SDG&E was going to deliver coal-powered electricity, adding more greenhouse gas emissions. “That is so false,” she said. “I have committed personally that we would not bring coal over the line.”

Grueneich and her allies were clearly outgunned. Peevey’s proposal had the support of dozens of San Diego area business leaders who appeared before the commission Thursday.

In addition to Sanders, San Diego Association of Governments Chairwoman Mary Sessom testified in favor of Peevey’s plan.  “There’s going to be a collision when demand exceeds what we can produce,“ Sessom, the mayor of Lemon Grove, said after her appearance. “It has some things that aren’t positive, but it is the best we have.”

Commissioners also heard pleas from Imperial Valley officials, who said Peevey’s proposal would help ignite new businesses in a region where one-in-four are unemployed. “With the green rush, there’s a lot of interest,” said Andy Horne, deputy chief executive officer of Imperial County. One geothermal plant could employ 40 people, he said.

“Renewable energy has always been beyond our reach – like a mirage in the desert,” said Imperial County Supervisor Larry Grogan. But times have changed, bringing hope of new jobs in clean industries, he said.  “When opponents to Sunrise come before you today,” Grogan continued, “I ask that you weigh their protests against the silent ones: the foreclosed, the unemployed, and this state’s commitment to fight global warming.”

San Diego leaders told the commission that the line is needed to ensure that the lights stay on. The region, Sanders told commissioners, relies on just a single power line and aging fossil-fueled plants for its energy. The antiquated system, he said, play a role in business decisions whether to locate in the region. “Energy reliability is a key consideration,” Sanders said.